Construction Schedule
Bids Due – 06/05/2025
Award Project: 06/24/2025
Notice to Proceed: 07/08/2025
Project Completion: 12/29/2025
PROJECT INFORMATION
Owner
Upper Moreland School District
ESTIMATED COST
GC
$300,000
HVAC
$60,000
Electrical
$70,000
Plumbing/FP
$85,000